Success at Arbitration - Residential Dispute, Kent

Our householder client had commissioned a design and awarded a contract for £241,000 for a high specification extension and refurbishment.  The contractor fell into delay and eventually ceased work.  He submitted a final account for £102,000 more than the contract sum. 

Metcalfe Briggs Surveyors was engaged by the householder and assessed the true value of the final account at £239,000.  We also determined that a substantial counterclaim of £45,000 for incomplete and low standard work was justified.

The contractor referred the matter to arbitration, during which the following issues were decided:

• Had the contract been terminated or repudiated?   Found in favour of the householder that the contract had been repudiated by the contractor.

• Should the contractor be allowed back to complete the works?  Found in favour of the householder, the contractor was not allowed to return.

• Payment due – found in favour of the householder that a substantial payment was due from the contractor to the householder.

• Standard of workmanship and completion – found in favour of the householder that there was £45,000 of incomplete or defective work.

• Damages – found in favour of the householder – general damages and costs were awarded.

Metcalfe Briggs provided detailed evidence during the hearing which formed a central part of the case decided by the Arbitrator.   Our client started with an incomplete, sub-standard project with a demand for £102,000 over budget and was facing expenditure of £45,000 to complete the works.  Success at arbitration meant our client was paid a substantial sum by the contractor and had all legal and professional fees reimbursed.  The householder was free, with funds to complete the works using alternative contractors.

Previous
Previous

Purchase and Repair Scheme – Harrow, Middlesex, HA2

Next
Next

Final Account Dispute - Offices London